The decision on a Turkish investor acquiring a stake in the Akkuyu nuclear power plant will be made as the first unit proceeds through its startup and operational stages. Rosatom Director General Alexey Likhachev told journalists this on the sidelines of the World Atomic Days forum in Antalya.
“The negotiations are currently being conducted in a confidential format, but I am confident that, in line with the stages of establishing and operating the first unit, a decision will also be made to change the financial and economic model, primarily with regard to the entry of a Turkish investor,” Likhachev said.
Stake of up to 49%
The head of the state corporation recalled that the intergovernmental agreement allows an investor to acquire a stake of up to 49%. The investor could be either a Turkish company or a company from a third country, subject to the consent of the Turkish authorities. “There are Turkish legal entities that have expressed such an interest,” he noted.
According to Likhachev, the entry of a Turkish investor would strengthen the project’s organizational and financial stability. At the end of October, Vladimir Putin said Turkish companies were ready to acquire a stake in the plant, into which Russia has invested $25 billion, RBC reported.

Fuel in December, electricity in early 2027
Rosatom is currently awaiting permission to conduct hot functional testing of the first unit. At this stage, the equipment is tested under normal operating parameters using an external power source, while fuel simulators are placed in the reactor instead of nuclear fuel. The tests will demonstrate the performance of the equipment and safety systems, as well as the readiness of the personnel.
“I very much hope that we will successfully complete these tests and that the loading of actual fuel into the first reactor vessel will begin in December, after which Türkiye will receive this long-awaited nuclear power in January or February,” Likhachev said, adding that it was too early to anticipate the test results. Work is also continuing on the station’s three other power units.

Meanwhile, Ankara is preparing its next nuclear projects: Deputy Energy Minister Zafer Demircan said contractors for the nuclear power plants in Sinop and Thrace would be selected shortly. Likhachev said Rosatom was discussing with its Turkish partners the further development of the country’s nuclear energy sector and possible participation by Russian companies in national plans.